Client background
Master Building Solutions is a licensed building company based in Marrickville, NSW, specialising in acoustic treatment for homes affected by traffic, industrial, rail and aircraft noise. They work alongside contractors and government agencies.
It won the tender for the Managing Contractor for the Western Sydney Airport Noise Insulation Program, funded by the federal Department of Infrastructure, Transport, Regional Development, Communications, Sport and the Arts. For homeowners living under the new airport's flight paths, the program is the difference between putting up with aircraft noise and having their home insulated against it.
The challenge
This was a brand-new program, so there was no old system to replace. Everything had to be built for the job, and a conventional sales-process CRM had no answer for it. One system had to work for three parties at once: the Master Building Solutions team running it, the federal department funding and approving it, and independent advisors reporting directly to the department.
Approval gates that couldn't be skipped
Each home moves through a project lifecycle, up to 18 months, with government funding approvals between phases. Every step had to happen in the right order, and be provable afterwards.
Federal record-keeping
As a publicly accountable program, records had to meet federal archival requirements.
Eligibility decided by location
Whether a home qualifies depends on where it sits in the program's eligibility area.
Why it mattered
The airport had a fixed opening: the first cargo flight on 27 July 2026, with passenger flights from 25 October. The federal government was funding the program on hard timelines to get the Noise Insulation Program under way before then, and the CRM had to be live within the first three months as part of the tender.
Our solution
We shaped Sales Cloud and Service Cloud around a government funding approval workflow, and connected the systems around it. Every phase (CRM, assessments and project delivery integration) was delivered on a custom milestone framework, built to their specification.
Applications straight from the website
Webplace's custom Drupal website connects to Salesforce via OAuth, so residents' applications flow straight into the system.
A process that runs itself, with people making the calls
Using Salesforce Flow Orchestration, we built a state-machine model. Whether an application comes in from the website or is entered by the team, it automatically creates the parent case and each sub-case in sequence, with approval gates between phases. The process is automated, the decisions aren't: department staff make each approval on the same platform, and orchestration work guides assign the steps for every stage to the right person.
Records that meet federal requirements
ShareConnect links Salesforce to SharePoint so documents are stored to federal archival standards.
Eligible properties loaded from day one
The program's list of eligible properties was pre-loaded into Salesforce. When residents enter their address on the website, the lookup matches it to that property record, so every application lands against the right home.
Project delivery in view
With ISV partner Aprika, we embedded Mission Control inside Salesforce, putting real-time Gantt charts directly on each case.
The results
Live in time for the program to open
Go-live was 23 April 2026. The first resident application came in two days later, three months ahead of the airport's first cargo flight, and applications peaked at 60 in May.
A whole program in one system
In its first six months the platform has taken on 140 applications, with 82 assessments and 218 case documents managed alongside them. The program team, the department and contractors all work from the same record. Every contact with a homeowner is captured, so the department can see the work behind each property, and every approval and upload is dated for the audit trail.
We capture all the contact points we have with all the different homeowners. It captures every little interaction.
Support that didn't stop at go-live
We worked through each iteration alongside the Master Building Solutions team and the department, so the build matched how the program runs. That included fitting in out-of-hours sessions with Mission Control's team in Seattle. Since go-live, we've stayed on hand for fixes and tweaks as the program grows.
Joe in particular was sensational. There was never a time when we felt we had to wait for something.
A system the team can grow themselves
Training on dashboards, reports and how the system fits together meant the team didn't stop at what was delivered. They've since changed page layouts, added new triggers and information, and are now building their own flows. With 77 projects running in Mission Control as works get under way, and the program running to 2029, every home follows the same gated process from application to finished works.
There were little things we were never going to capture in that first three months, and it's worked well because we've been able to go in and just add those little bits of detail we need.
In short
Master Building Solutions is running a federally funded program through to 2029, with the department and contractors all working from the same system. It was live before the first plane landed, and the team is now shaping it themselves as the works get under way.